The reconstruction project of 5R/23L has been delayed until spring 2013.  This delay will allow longer use of the ILS this year and stage the grant funding so that the runway project can possibly be completed in 1 – 2 years rather than the scheduled 3 year plan.

23R/5L will be closed for the next 40 days as of September 19 for preliminary construction work. In the interim, plans are to have a VASI or PAPI installed on 23R.

Storm drainage projects will be ongoing on the northeast end of the airport.

Wind Cone insallation with LED lighting as part of the 5R/23L Reconstruction Project will continue. Contractors have begun this work and are expected to have the 8 planned lighted wind cones completed soon.  Look for them at the approach end of every runway end at Willow Run.

Sealing of pavement cracks on Hotel and Bravo will be starting next week weather permitting.

Wayne County Airport Authority has announced their new CEO, Tom Naughton.

Elgene W Doinidis, ASN Volunteer, Willow Run Airport

Advertisements
No comments yet

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: